Monday, September 8, 2008

Nearly Locked Up!










Hi All,


Its been 1 week and the brickwork of our house is finished! Only thing left to get to lock up is for the Front door & the internal access door to be installed!


The inside fit-out has also started; the electrical, gas & power switches have been wired through the house, the heating & aircon vents are in & the bath tub has arrived!


Here are some more pics to keep you entertained...

Sunday, August 31, 2008

Roofs Up!




Hi guys,


Its now nearly 1 month since we started & our guttering & roof tiles have gone up!


All is looking very good & more & more like a house!


The bricks & the sand for the cement has been delivered too, so hopefully the rain will stay away & they can make a start on the bricks too!


We're now getting very excited!


Can't believe how quickly its coming along - fingers crossed they keep up this pace.


Sunday, August 3, 2008

Stage 2 - Frame completed

















Hi All,


Its the 02/08/08 and the trusses are up & the frame is complete!


And to top it off the windows & sliding doors have been delivered & installed too...

We've had an independent inspection & have noted some minor adjustments that need to be made: a few nails for additional support in the outer corner studs, bracing to the upper trusses & central support packing blocks under the windows to stop them bowing.

The roof & bricks should only be days away....

Monday, July 28, 2008

Frames up!


Ok, here we are!


Our building site is finally starting to look like a house!


The frame of the walls has quickly gone up on the 27/07/08.


Its all looking good for Christmas move in, just as long as they get the roof trusses up!




Saturday, July 19, 2008

We have lift-off!


Here we are 3 months after we finally picked our house, following endless months of viewing display homes.

If you don't already know, we fell in love with & decided to build the Rouge 340 by UrbanEdge Developments.

We've managed to get through the plan alteration, the tender, the contract & the finance approval & finally have some movement on our block in Ulmara on the Maribyrnong.

It all started with some soil movement & a porta-loo on the 11/7/08 , followed by digging & installation of pipes on the 14/7/08, then mesh, wire & waffle pod was visible on the 17/7/08.

But the real excitement began with the laying of our slab on 18/7/08.

Next installment.... the frame.... fingers crossed.